Door Access Control / Interactive field guide
Cloud Access Control Migration Guide for Multiple Sites
Plan a multi-site door access migration with a verified inventory, approved credentials, pilot doors, phased cutover, and legacy system handover.

What you’ll leave with
A wave plan with a current door inventory, approved credential transition, supervised acceptance, and a documented retirement decision.
- Reconcile physical openings, approved occupants, and business workflows before ordering.
- Verify a representative pilot and give each migration wave explicit release and acceptance owners.
- Reconcile active and retired permissions and preserve the approved operating records after cutover.
A door access migration changes how people enter buildings while those buildings still have work to do. Employees might use several sites, two locations might share a visitor desk, and a facility may have additional approvals before anyone can change an opening. Plan the transition around those responsibilities. A platform order and a list of doors give the project a start, while the release plan determines when each site is ready to switch.
Use this guide to build a scope for moving from an existing electronic access system to cloud-managed door access. The same planning approach helps when several locations currently use different systems. Gather site counts, asset records, and examples of approved staff roles. Route detailed drawings, schedules, credential data, and occupant lists through the project's approved channels.
Put this guide to work
Build a migration plan for cloud door access
Identify who can approve the move, what has to carry forward, and how your team will accept each group of sites.
0 of 3 decisions entered
Choose an answer to each question to generate your brief.
Your project brief
Complete the choices above to prepare your brief.
Your entries stay in this tab. If you add the brief to a quote, you can edit or remove it before submitting. BlueHouse receives the project notes you submit. Reloading clears unsent entries.
1. Reconcile each opening and assign a site decision maker
List the openings in scope by site and give each a stable reference that facilities and the installer can reconcile during the survey. Capture its purpose, who uses it, and whether another building system or property owner is involved. Mark hardware, reader, credential, and coordination items as current, verified reusable, replace, or needs review. Give the proposed installer time to document issues that affect the installation schedule or quote.
Work with the site's authorized contacts to check that existing diagrams and schedules agree with what is installed. A recent remodel may have changed a door's use or shifted responsibility to a property manager. This affects the work even when the old platform describes the door correctly. Ask who approves the new design, which maintenance window is available, and how staff will receive notices about a temporary change.
Ask the bidder to describe responsibilities for networking, building requirements, installation, and operation in the same scope. Request a list of each retained component with supporting compatibility evidence. Give each dependency an owner and a release date. Resolve each site approval before the project issues equipment or announces a cutover window that depends on it.
2. Establish who approves people, credentials, and dates
Start with an approved roster, then reconcile the existing user and credential records against it. Decide who can validate an employee, authorize a contractor, and close an expired assignment. Some people may hold more than one credential or work in several locations. Keep a place in the worksheet for that relationship so a total count of people can be reconciled separately from a total count of cards and mobile credentials.
Determine what each site needs from its employees during the transition. If the project retains cards, document the verified equipment and credential compatibility for each approved group. If a group receives new cards or mobile credentials, include distribution, enrollment support, and accommodations for people who need an alternate approved credential. Confirm the change with staff who work outside normal office hours before fixing its date.
A bulk import can reduce manual work when the actual platform supports it and data is clean. Verkada documents CSV imports that associate credential records with access users. Use a synthetic or approved pilot list to check how your chosen system handles identity matching, duplicates and exceptions before authorizing production records. Have an accountable privacy or records owner approve any transfer of personal data.
3. Set up ownership for provisioning and local work
Write down which system approves each kind of access. An employee directory can be authoritative for employee records while local staff still handle approved contractors. Have security, HR and IT agree on who owns assignment of entry permissions and what happens when a person changes teams, works at another location, or leaves. Name a contact who can review a pending change if a directory connection reports an error.
If you plan to connect an identity provider, verify the specific provisioning feature in the proposed platform and licenses. Microsoft recommends starting automatic provisioning testing with a small set of users before wider production rollout. Have the integration owner confirm how an approved new test user arrives, what changes when its role is updated, and how removal is reflected in the physical access system.
Local delegation needs a separate check. Verkada's documentation describes organizing users and groups into directories to scope administrative work. Ask the bidder to demonstrate the roles for your exact organization, site, and tenant boundaries. Use an ordinary authorized account to confirm the ability to perform an approved task and check that unrelated site records remain outside the user's access.
4. Work through a fictional three-location rollout
Suppose a property group manages 24 controlled openings across three sites. A small office has four, an occupied branch has eight, and an operations building has 12. The small office is first because the facilities team can supervise a pilot there. The office uses both employee card and mobile access. The team will validate the branch's guest workflow before that site's release because the pilot office has no visitor desk.
The current roster export contains 145 people. The business owner approves 125 active records to migrate, sets 12 aside for further review, and confirms eight should be excluded because they no longer need access. Those categories account for all 145 people. The installer maintains a separate credential count because some people already have both an approved mobile method and a physical card. Set an escalation date for the 12 unresolved people so the sites can prepare.
The team sets a review meeting after each stage. At the pilot site, the owner reviews the opening records and provisioned roles before agreeing to release the next group. The second stage then confirms the staffed visitor desk and reporting process. The operations site moves last when its shift leads can review the intended cutover and accept the release. The sequence is an example that illustrates how approval dates can control the schedule.
If two openings at the branch need additional review, the branch wave can remain open while the responsible people evaluate them. In this example, the completion record would then show four accepted pilot openings and six accepted branch openings, for ten accepted in all. Keep the two pending branch openings visible in the schedule and revisit the date of the operations wave with the site owners.
| Wave in the example | Openings | Evidence for the next decision |
|---|---|---|
| Pilot office | 4 | Approved entry methods, delegated role and ordinary staff tasks demonstrated. |
| Occupied branch | 8 | Additional visitor workflow and branch reporting reviewed by their owners. |
| Operations building | 12 | Shift coverage, handoff records, and operation accepted by facilities. |
| Total | 24 | Inventory and acceptance records reconcile to all openings in scope. |
6. Verify retired access and preserve required records
Once the new site operates as planned, reconcile its roster and permissions with the approved scope. Include retained cards, reissued credentials, temporary access and people who still work at sites awaiting migration. If two systems operate during the transition, designate a responsible person to handle changes in both and confirm they take effect in the correct locations. Document when that overlap ends at each site.
Verify building access and administrator accounts as separate outcomes. Verkada documents that suspending a person from Access Control affects entry and its Pass app while access to other products can still permit a Command login. Ask the access owner and IT owner to check what the corresponding action does in the selected system. Save the authorized verification record with the handoff evidence.
Have the records owner review event histories, replacement platform exports, and the expected retention schedule before retiring the old system. Select the information the business needs and confirm that an authorized person can interpret it. Record the date the legacy contract or hosting arrangement ends and who removes retired accounts and equipment after acceptance. Any records retained for an approved business need should have an owner and a defined storage location.
Ask supervisors to check the first scheduled access review after the change. A site may need help handling a door assignment, correcting a roster mismatch, or finding the right report. Document who takes each issue from intake to resolution. Have the operating team acknowledge that it can maintain ordinary changes and escalate exceptions before the installer closes the work order.
7. Request a quote by site and migration wave
Ask bidders to separate the costs of the site survey, retained or replacement hardware, installation, credential issuance, identity integration, training, launch support, and recurring licenses. Size the quote for the known site groups and identify items that depend on further survey. Ask whether there is a temporary period in which both systems require paid support. Compare proposals using the same expected responsibilities and time period.
Give BlueHouse Telecom the number and types of sites, approximate opening counts, current platform, desired credential methods, and target windows. Identify the staff who need local administration and the integrations that the business relies on. A migration scope can then tie equipment and staffing decisions to the dates and acceptance outcomes your facilities team will use.
Common questions
Can a business move to cloud access control in phases?
Many projects can use a pilot and subsequent site waves. Confirm in the planned design which systems will operate during overlap, how credential changes are administered, and who approves each release.
Do employees need all new cards for a cloud access control migration?
Credential reuse depends on the proposed reader, controller, credential, and requirements. Ask the installer to verify the exact combinations and demonstrate supported reuse before ordering replacement quantities.
Who should sign off before an access control cutover?
Name the operations owner and qualified building contacts, then give each organization involved a decision and an acceptance responsibility. Have them review the scope, approval records, cutover window and verification evidence.
What happens to records from the legacy system?
Ask the records owner to review the export options, approved retention needs and who must be able to read any retained report. Plan that handoff in the quote and verify it before closing the old agreement.
Sources & accuracy notes
Source information reviewed . Confirm compatibility, availability, and commercial terms for the proposed equipment. Planning tools organize your assumptions; the site survey and agreed design establish the final scope.
- Verkada access credential CSV import and export documentation
- Microsoft Entra guidance for planning automatic user provisioning
- Verkada Command directory scope for role management
- Verkada distinction between suspending door access and retaining product account roles
- Avigilon Alta Access reporting and export options
Have a correction or a project question? Email BlueHouse about this guide.